Welch Rd. Changes July 1, 2013

June 21st, 2013

Welch Road Will Return to Two-Lane, Two-Way Traffic Permanently Mid-July


The Welch Road Utility Project, which includes new and upgraded utilities, the widening of Welch Road, and
other improvements to support the future new hospital facilities, is scheduled to complete construction four
months earlier than originally scheduled. In order to accommodate final construction, one-way traffic on Welch
Road will shift to the outboard lane on Monday, July 1, 2013. This shift will remain in effect until Welch
Road opens to two-lane, two-way traffic in mid-July.
Traffic changes include:

• One-way traffic on Welch Road will shift to the outboard lane on Monday, July 1, 2013 in order
to accommodate final construction of the inboard side of Welch Road. During this time ALL vehicle and
pedestrian access will be on outboard Welch Road. Inboard Welch Road will be closed to through traffic.
• The Welch Road driveways to 750 and 770 Welch Road will open Monday, July 1, 2013. The
temporary driveway from Vineyard Lane into these properties will permanently close effective
Tuesday, July 23, 2013.
• The Welch Road driveways to 730 and 732 Welch Road (Packard Clinics and Outpatient MRI Center)
will remain closed indefinitely. The Vineyard Lane driveway into these properties will remain open.
• Welch Road will permanently open to two-lane, two-way traffic in mid-July.

Welch Rd. July 1, 2013