  • Net increase in Stanford Hospital and Clinics: 824,000 sf
  • Net increase in Lucile Packard Children’s Hospital: 442,000 sf
  • Total floor area after construction: 3.7 million sf
  • Net addition: 1.3 million sf
  • Height of new Stanford Hospital and Clinics pavilions: 130 ft
  • Height of new Lucile Packard Children’s Hospital pavilions: 85 ft
  • New employees: 2,242
  • New beds: 248
  • New parking spaces: 2,985
  • Net increase in parking spaces: 2,053
  • Construction workers at Stanford University Medical Center sites: 2,200
  • Public hearings scheduled on the Draft Environmental Impact Report: 11
  • Protected Palo Alto trees at risk: 71
  • Intersections that would have “unavoidable significant impact” because of the project: 3

This is the fourth article in a four-part Palo Alto Weekly cover story. To download the complete cover story, please click here.